The TPs were the last in a total of 60, all of which were delivered according to schedule.
The production of the 60 TPs included electrical design and have all been shipped from Aalborg Harbor to Sassnitz for storage since 2017, before the final installation this fall.
The Offshore Wind Farm will have a total capacity of 385 MW and will be located in the Baltic Sea approximately 35km north of Germany’s largest island, Rügen.