Gode Wind transition pieces
13 transition pieces upended at the Bladt harbour facilities in Aalborg...
19 December 2014
The first transition pieces for DONG Energy’s Gode Wind offshore wind farm are now lining up at the harbour at Bladt Industries’ facilities in Aalborg. 13 of the 97 transition pieces are being upended this week by the Bladt-team.
The transition pieces, with a diameter of six meters and a height of approximately 30 meters, will weigh in well over 500 tonnes when completed.
Bladt Industries is fabricating the 97 transition pieces in Aalborg while our subcontractor EEW is fabricating the 97 monopiles in Rostock.