Nordsee Ost on the barge.
Nordsee Ost – a successful race against time
This July the Bladt team had the pleasure of yet another successful project closure, as the Nordsee Ost substation left Bladt Industries headquarters in Aalborg, Denmark.
21 August 2014
The 1,800 tonnes substation was an exciting challenge for Bladt Industries to complete, as the goal was to finalize the project within 16 months – a very short time frame to conduct a project of this calibre.
However, close cooperation and efficiency between Bladt Industries and the client RWE enabled Bladt Industries to finish the substation in due time.
Hence, as scheduled, Nordsee Ost left Bladt Industries on the barge Tuesday, July 15. The substation has now been installed in the final destination in the German North Sea.