CS WIND Offshore News

Successful installation of the Kaskasi substation.

The 1,400 tonne Kaskasi substation has been successfully installed in the German North Sea some 35km north of Helgoland. Here 38 wind turbines will be connected to the substation that will have a capacity of 342 MW.

28 March 2022

We have been busy with Kaskasi since May 2019 – and by now, we feel that we know each inch of this 1,400 tonne yellow beauty.
Please enjoy the amazing photos from Kaskasi’s journey to the installation site. The journey started at our site in Aalborg and it passed by the Semco Maritime headquarters in Esbjerg, where they also got a glimpse of Kaskasi in the sunset.
Thank you to the entire project team for a fantastic and dedicated effort!

About Bladt Industries
Bladt Industries is a leading supplier within offshore wind turbines. In the last 25 years, the company has delivered more than 2,500 offshore wind turbine foundations, equivalent to more than a third of all the world's offshore wind turbines. Bladt Industries has also supplied a significant number of offshore substations for offshore wind farms. Bladt Industries is the foundation for the green energy transition offshore.

For more information
Rikke Tikjøb1

Rikke Tikjøb Christiansen

Chief People & Culture Officer

Tel.: +45 4083 7583

Email: