Borkum Riffgrund 3 & Gode Wind 3
Germany (451 MW)
Reference
Bladt Industries has secured a contract to deliver XXL monopiles for two of Ørsted's offshore wind farms located in Germany. The XXL monopiles will be used in the construction of the two offshore wind farms, Gode Wind 3 (242 MW) and Borkum Riffgrund 3 (900 MW).
Bladt Industries wins the order together with the German steel contractor Steelwind. Each XXL monopile will stand up to approximately 100 metres in height with a diameter of almost 10 metres and a weight of approximately 1,200 tons.
We performed the last load out of the final monopiles in October 2024.
Gode Wind 3 and Borkum Riffgrund 3 are expected to be completed in 2024 and 2025, respectively.
Client:
Ørsted
Scope:
41 XXL monopiles
Year:
2022
Length:
Up to 95 m
Diameter:
10 m
Total weight:
51,200 t